SELF CLIMBING HYDRAULIC FORM (SCHF) was used for construction of an entire core on a fourty-nine story high rise. |
|
Project: One Wall |
Project Owner: General Contractor: Forming Contractor: |
| Self Climbing System allowed concrete forming contractor, Loewens' Construction Ltd., to pour floor slab and core wall forms on the same slab in one day instead of four. | |
Four cylinders with a single stroke of up to 12 feet, lift the entire outside and inside 135,000 lb wall form system, 76’-9” long by 21’-0” wide, at the speed of 2 ft/min.
|
![]() |